On September 15, 1995, construction began on the Alafia River Oyster Bar Restoration Demonstration Project. The intent of the project was to re-establish oyster bars in the lower Alafia River which have historiclly been lost to dredging of the shipping channel and associated turning basin adjacent to Cargill Fertilizer Company. The progress of these oyster bars has been monitored quarterly over a three year period.
Title: Alafia River Oyster Bar Restoration Demonstration Project.
165 views
32 downloads
Name(s): Cardinale, Tom.
Ash, Tom.
Tampa Bay Estuary Program
Type of Resource: text
Genre: Technical Report
Issuance: multipart monograph
Publisher: Environmental Protection Commission of Hillsborough County
Place of Publication: Tampa, FL
Physical Form: print
Extent: 24 p. ; 28 cm.
Language(s): eng
Summary: On September 15, 1995, construction began on the Alafia River Oyster Bar Restoration Demonstration Project. The intent of the project was to re-establish oyster bars in the lower Alafia River which have historiclly been lost to dredging of the shipping channel and associated turning basin adjacent to Cargill Fertilizer Company. The progress of these oyster bars has been monitored quarterly over a three year period.
Identifier: 44483243 (oclc), fgcu_swfe_0338 (IID), AAA3538 QF
Note(s): prepared for Tampa Bay Estuary Program [by] Tom Cardinale and Tom Ash, in cooperation with Suzanne Cooper.
"February 15, 1999."
Final monitoring report. September 1995-December 1998.
Subject(s): Oyster culture -- Florida -- Alafia River
Charlotte Harbor Information Resource Center documents
Held by: SUS01 FCL01
Held by: SUS01 FCL01
Persistent Link to This Record: http://purl.flvc.org/fgcu/fd/fgcu_swfe_0338
Use and Reproduction: http://rightsstatements.org/vocab/NoC-US/1.0/
Host Institution: FGCU
Is Part of Series: Technical report (Tampa Bay Estuary Program) ; no. 01-99.